Kodo construction status as at July 2018.

  • Jump form at Level 28
  • Floor Level up to Level 24 part poured
  • Structural Steel Level 24 complete
  • Formwork is at Level 24
  • Reinforcing to Level 24 completed
  • Fitout is at various stages through Level 2 to 20
  • Façade to Level 20 completed